Project Overview
Welcome to the official community information page for the City Centre Urban Development construction project, located at the junction of Church Lane and Carter Road.

This project involves the development of a 10-storey facility with an integrated basement level. Once complete, the centre will provide a modern office space, including staff offices, retail shops and an underground carpark

Construction Timeline (Estimated)
Phase Start Date End Date
Site Setup & Hoarding 03 March 2025 28 March 2025
Basement Excavation & RC 01 April 2025 31 August 2025
Superstructure Frame 01 September 2025 31 January 2026
Façade & Roofing Works 01 November 2025 30 April 2026
Internal Fit-Out & MEP 01 February 2026 31 October 2026
Landscaping & External Works 01 September 2026 15 November 2026
Site Demobilisation 16 November 2026 30 November 2026

Anticipated Completion Date: 30 November 2026

What to Expect During Construction
Working Hours:

Monday to Friday: 08:00 – 18:00

Saturdays: 08:00 – 13:00

No works on Sundays or public holidays without prior notice

Traffic Management:

Temporary footpath closure on Carter Road (March 2025 – August 2025)

All deliveries scheduled and managed via an on-site Traffic Management Plan

Marshalling staff present during peak delivery windows

Noise and Dust Control:

All activities will comply with BS 5228: Noise Control on Construction Sites

Dust suppression systems and wheel-wash facilities in place

No high-impact demolition or piling works after 5 PM

Lighting:

Minimal low-level site lighting will be used for safety

No overnight floodlighting unless in emergency

Community Considerations
We are committed to minimising disruption and ensuring safe conditions for nearby residents, schools, and businesses. Here’s what we’re doing:

Regular street cleaning to remove mud and dust

Noise monitoring points installed along Church Lane

Security patrols outside of working hours

Weekly newsletter updates posted to this site and sent to subscribed residents

Local employment & apprenticeships encouraged through our construction partners

Contact Information
If you have any questions, concerns, or would like to report an issue, please contact:

Community Liaison Officer:
Emma Reid
emma.reid@Imperium.co.uk
0800 123 4567 (Mon–Fri, 08:30–17:00)
On-site drop-in hours: Tuesdays & Thursdays, 10:00–13:00 (Site Office, Carter Road Entrance)

Out-of-Hours Emergency Contact:
Site Security: 07700 900123 (available 24/7)

Frequently Asked Questions (FAQs)
Q: Will construction affect my bin collection or utilities?
A: No disruptions are expected. We have coordinated with local services to maintain normal operations.

Q: Will you be working weekends?
A: Approval for Saturday mornings for quiet works have been approved.

Q: Can I access the footpath during works?
A: The Carter Road and Church Lane footpath will be diverted between April–August 2025. Signage and barriers will be in place for your safety.

Stay Updated
Subscribe to our weekly updates: Sign Up Here

Read the latest community newsletter: Download PDF – March 2025

Follow progress photos and updates via @EnglemereSite on X (Twitter)

Delivered by:
Imperium Developments Ltd
On behalf of the CLM Trust
Registered Office: 123 Fleet Street, London, EC4A 2BB